Friday, June 10, 2011

Woodland Construction Update - Woodland Drive

Woodland Drive will be under construction throughout the summer. This will have impacts on traffic and subdivision access. In order to keep the public updated on this project, I will post weekly project construction updates which are supplied by the Project Engineer.

Weekly Construction Update

Traffic Impact: Woodland Drive will be closed to through traffic from CTH M to Manchester Crossing. The construction limits are from 200-feet south of Cobblestone Lane to 200-feet south of Manchester Crossing. This closure will be in effect for the duration of the construction project. The anticipated completion date is September 30, 2011. Motorist can expect to encounter daytime flagging operations and potential delays. Access will be maintained through the work zone for residents and emergency vehicles. The best way to access Woodland Drive for the first two weeks will be Mill Road or CTH M.

Work Completed since last update: June 2, 2011 to June 9, 2011June 2, 2011 to June 9, 2011 -  The utility companies, (TDS, Charter, MG&E – Gas, MG&E – Electric, Waunakee Utilities, and Alliant Energy) continue to relocate their facilities in preparation for the Woodland Drive project. The utility work will continue through the month of June.The utility companies, (TDS, Charter, MG&E – Gas, MG&E – Electric, Waunakee Utilities, and Alliant Energy) continue to relocate their facilities in preparation for the Woodland Drive project. The utility work will continue through the month of June.

The Department awarded the contract to Meise Construction, Inc. (Prime Contractor) and the contract has been executed. The Woodland Drive Improvement project will begin Monday June 13, 2011.

Anticipated work schedule for next week: June 9, 2011 to June 16, 2011 The Department awarded the contract to Meise Construction, Inc. (Prime Contractor) and the contract has been executed. The Woodland Drive Improvement project will begin Monday June 13, 2011. Anticipated work schedule for next week: June 9, 2011 to June 16, 2011June 9, 2011 to June 16, 2011 The mobilization of equipment, staging of equipment and traffic control will begin.The mobilization of equipment, staging of equipment and traffic control will begin.

Moore Surveying will start construction staking throughout the project limits.Moore Surveying will start construction staking throughout the project limits. Voegeli Landscaping along with Meise Construction will install erosion control throughout the project limits.Voegeli Landscaping along with Meise Construction will install erosion control throughout the project limits. Meise Construction will start removing trees (clearing and grubbing) throughout the project limits.Meise Construction will start removing trees (clearing and grubbing) throughout the project limits. Meise Construction will start pavement removal and grading operations (common excavation) from Mill Road to the north project limits.Meise Construction will start pavement removal and grading operations (common excavation) from Mill Road to the north project limits. Utility Line Openings (ULO) will begin throughout the project limits to explore potential storm sewer conflicts.Utility Line Openings (ULO) will begin throughout the project limits to explore potential storm sewer conflicts.

Summary: Starting Monday, there will be construction activity occurring on the project from Mill Road to Manchester Crossing. The survey firm working on the project will be working the length of the site. Additionally, the contractors will be removing trees and installing silt fence along the entire length of the project. As soon as this initial work is completed, the contractors will begin grading the road from Mill Road to the north project limits. When this work begins, it will be very difficult to get through this part of the project and delays are excepted. Access will always be maintained for the residents and businesses but the roadway will be closed to through traffic.Starting Monday, there will be construction activity occurring on the project from Mill Road to Manchester Crossing. The survey firm working on the project will be working the length of the site. Additionally, the contractors will be removing trees and installing silt fence along the entire length of the project. As soon as this initial work is completed, the contractors will begin grading the road from Mill Road to the north project limits. When this work begins, it will be very difficult to get through this part of the project and delays are excepted. Access will always be maintained for the residents and businesses but the roadway will be closed to through traffic.