Woodland Drive Update for This Week

Click on this link to view the latest project update for the Woodland Dr. construction project:

http://www.egovlink.com/public_documents300/waunakee/published_documents/Public%20Works%20Documents/WoodlandProjectUpdate/No%2017_092911%20to%20100711_Complete.pdf

Additional information from the project engineer:

The paving operation is scheduled to resume next week. The contractor will start with the multiuse path from Cobblestone Lane to Tierney Drive, and then start the binder (lower layer) in the same area. During the binder paving operation travel between Cobblestone Lane and Tierney Drive will again be a challenge. Please allow extra time and expect delays.

The week of October 10, 2011 the contractor will begin the surface (upper layer) for the entire project. The contractor anticipates starting at Tierney Drive working south. When this is complete the contractor will pave from Tierney Drive working north, and at this time all traffic will enter and exit from the south with the exception of the Emerald Grove Lane residents. Please allow extra time and expect delays.

I will send out the anticipated daily schedule for the paving operation the night before and the changeable message boards will be used to assist with the traffic flow.